Benchmark Raises Hut 8 Price Target After Bitcoin Miner Signs
Bitcoin Magazine Benchmark Raises Hut 8 Price Target After Bitcoin Miner Signs $9.8 Billion AI Data Center Deal Bitcoin miner Hut 8's stock will soar due to its AI ambitions, according to investment bank Benchmark. This post Benchmark Raises Hut 8 Price Target After Bitcoin Miner Signs $9.8 Billion AI Data Center Deal first appeared on Bitcoin Magazine and is written by Mathew Di Salvo .
TL;DR
Microsoft withdrew from Nscale’s £2 billion Loughton data centre after UK grid delays pushed power supply to the early‑mid 2030s, removing a tenant that represented about $43.8 billion of Nscale’s backlog and threatening its NYSE listing and valuation.
Key facts
- Microsoft terminated its lease for Nscale’s Loughton data centre on 22 July 2026.
- The Loughton site was designed for about 90 MW of power and slated to open in 2027.
- Power supply for Loughton will not be available until the early‑mid 2030s.
- Microsoft’s lease represented roughly $43.8 billion of Nscale’s $103.4 billion backlog.
- Nscale’s NYSE listing targets a $35 billion valuation and a $3 billion raise.
Microsoft has terminated its agreement to anchor Nscale’s planned £2 billion data centre in Loughton, Essex, after power grid delays pushed the site’s electricity supply back to the early‑mid 2030s. The cancellation was reported on 22 July 2026 and removes a tenant that had committed to lease 23,000 Nvidia AI chips at the facility, a move that threatens Nscale’s upcoming New York Stock Exchange listing and its valuation targets.
Background
Nscale, an AI‑focused cloud startup founded in 2024 by Josh Payne after spinning out of Arkon Energy, quickly built a reputation through partnerships with Nvidia and Anthropic. The company announced a £2 billion data centre project in Loughton, Essex, designed to deliver about 90 MW of power and originally slated to open in 2027. Microsoft was to be the anchor tenant, planning to lease 23,000 Nvidia AI chips, a commitment that represented roughly $43.8 billion of Nscale’s reported $103.4 billion contracted backlog. The Loughton project formed a central pillar of Nscale’s S‑1 filing, which was submitted on 18 September 2026 as the firm prepared for a NYSE listing targeting a $35 billion valuation and a $3 billion raise. However, UK Power Networks indicated that sufficient grid capacity would not be available until the early to mid‑2030s, a delay that effectively nullified Microsoft’s lease. Nscale also faces operational shortfalls at its flagship Glomfjord, Norway facility, where only 6.4 MW of the planned 30 MW is live, leading to penalties. These infrastructure challenges raise questions about the company’s ability to convert its large backlog into revenue within the timelines expected by investors.
What happened
On 22 July 2026, Cryptobriefing reported that Microsoft terminated its agreement to anchor Nscale’s planned £2 billion Loughton data centre, citing power grid delays that push electricity availability to the early‑mid 2030s. The original plan called for Microsoft to lease 23,000 Nvidia AI chips at the Loughton site, which was designed for about 90 MW of power and scheduled to open in 2027. UK Power Networks confirmed that sufficient power would not be supplied until the early to mid‑2030s, describing the grid connection problems as severe. Nscale’s S‑1 registration, filed on 18 September 2026, listed a contracted backlog of $103.4 billion, with Microsoft accounting for approximately $43.8 billion of that figure. The loss of the anchor tenant removes the only announced customer for Loughton, leaving the project without a clear revenue source. Nscale remains committed to the Loughton project and is seeking alternative power sources, but the cancellation may dampen confidence in its ability to deliver on its backlog. The company also faces operational delays at its Glomfjord, Norway facility, where only 6.4 MW of the planned 30 MW is live, already triggering penalties. These combined setbacks raise concerns for investors evaluating Nscale’s upcoming NYSE listing and its targeted $35 billion valuation.
Market impact
The termination of Microsoft’s lease removes a tenant that represented roughly $43.8 billion of Nscale’s $103.4 billion contracted backlog, a reduction of about 42 percent of the reported backlog value. Nscale’s planned NYSE listing targets a $35 billion valuation and a $3 billion capital raise, figures that may be reassessed by the market in light of the Loughton setback. The delay in power supply to the Loughton site, now pushed to the early‑mid 2030s, also postpones the activation of 23,000 Nvidia AI chips, potentially affecting demand for Nvidia hardware and related AI cloud services. The operational shortfall at Glomfjord, where only 6.4 MW of a planned 30 MW is live, has already triggered penalties, suggesting further financial strain. Investors may adjust pricing models for Nscale’s shares, and the broader AI infrastructure market could see a slowdown in projected capacity additions as power grid constraints become more prominent.
Why it matters
The loss of Microsoft as an anchor tenant undermines confidence in Nscale’s ability to convert its sizable backlog into near‑term revenue, a key factor for investors assessing the upcoming NYSE listing. The power grid delay highlights a systemic bottleneck in the UK’s energy infrastructure that could affect other AI‑related data centre projects, potentially slowing the rollout of AI compute capacity across Europe. Nscale’s reliance on a single large counter‑party for a substantial portion of its backlog exposes it to concentration risk, and the Glomfjord penalties illustrate operational execution challenges that may further erode investor trust. Together, these issues could lead to a reassessment of Nscale’s valuation, affect its fundraising prospects, and signal broader market caution for AI infrastructure firms facing similar grid constraints.
DeFi Intel’s take
Editorial analysis, not a statement of fact.
DeFi Intel's take: the abrupt termination of Microsoft’s lease suggests that Nscale’s growth narrative may be more fragile than its S‑1 filing implies. We read this as a signal that power‑grid constraints are a material risk for AI‑focused data centre developers, especially when large contracts hinge on timely electricity delivery. The concentration of nearly half of Nscale’s backlog in a single tenant also raises concerns about revenue diversification. While the company remains committed to finding alternative power sources, the market may price in a higher discount to its $35 billion valuation target until clearer pathways to power and revenue materialise.
Sources used for this analysis
DeFi Intel wrote this analysis from the reporting above. Any figure or quotation can be checked against those pages.
Frequently asked questions
Why did Microsoft cancel its agreement with Nscale?
Microsoft cancelled because UK Power Networks indicated that sufficient electricity for the Loughton data centre would not be available until the early to mid‑2030s, making the planned 2027 opening infeasible.
What proportion of Nscale’s backlog was tied to Microsoft?
Microsoft accounted for approximately $43.8 billion of Nscale’s reported $103.4 billion contracted backlog, representing roughly 42 percent of the total backlog value.
How does the power delay affect Nscale’s NYSE listing plans?
The delay removes the only announced customer for the Loughton site and raises doubts about Nscale’s ability to deliver on its backlog, potentially prompting investors to reassess the company’s $35 billion valuation target and $3 billion fundraising goal.
Direct answers
Short answers, written to be quoted.
- What caused Microsoft to pull out of the Nscale data centre deal?
- Power grid delays in the UK mean electricity for the Loughton site won’t be available until the early‑mid 2030s, leading Microsoft to cancel its lease.
- What impact does the cancellation have on Nscale’s IPO plans?
- The loss of its anchor tenant raises doubts about Nscale’s ability to meet revenue targets, potentially affecting its planned NYSE listing, $35 billion valuation target, and $3 billion fundraising goal.
DeFi Intel is an entity-graph aggregator: we curate, tag and link crypto news to a typed knowledge graph of protocols, tokens, people and incidents. We do not republish the full article body. Use the link above to read the original report at Bitcoinmagazine.
Entities in this story
Discussion
Comments are reviewed before publication.
Want the full article?
Continue reading on Bitcoinmagazine →
No comments yet.